Forkers Limited Civil And Ground Engineering
 
 


News


March 2009
 

Achilles ‘Verify’ Audit.

Our 2009 Achilles UVDB ‘Verify’ audit was carried out during March and excellent scores ranging from 95% to 98% were achieved for our Quality, Environmental and Health & Safety practices and procedures.


March 2009
 

Step Shaft Mine Gallery Infilling, Dudley

We have recently been awarded the £750k contract to complete the temporary stabilisation and infilling of Step Shaft Mine Gallery in Dudley. Step Shaft Mine is one of the many limestone mines that were mined in the area during the industrial revolution and which have remained open ever since. The 100m long by 15m high gallery has recently deteriorated to such an extent that it is being temporarily filled with sand to prevent further collapse. Dudley hope that funding will be secured to complete full stabilisation of the gallery and allow it to be reopened to the public as part of a larger canal based tourist attraction.


February 2009
 

Streetsbrook Road Flood Alleviation, Solihull

Following a long period on the drawing board, we have recently commenced a major foul water flood alleviation project for Severn Trent Water in the Streetsbrook Road area of Solihull. The £3.1m scheme will last for 40 weeks and includes 3 large shaft storage tanks up to 20m deep and 2.5 km of open cut sewers up to 900mm dia in carriageway.


February 2009
 

EGE Press Project, Honda, Swindon

Despite the downturn in car sales, Honda is investing in additional production capacity for an anticipated new model to be built at its Swindon Plant. We are currently completing a £1.1m contract to construct a new 20m x 10m x 9m deep Press Pit and conveyor tunnel as part of this extension. This follows a number of other work packages that we have completed as part of the extension of the manufacturing facility over the past 6 months.


January 2009
 

Aidrie to Bathgate Rail Line – Mining Remediation Work

The 5th January saw the commencement of a £5.5m advance works contract for Network Rail (Scotland) to complete mine workings and mineshaft stabilisation work on the disused railway line which is to be re-opened following complete re-construction. This project is being carried out in 11 treatment areas of heavily worked coal and fireclay mine workings along the route of the 40km line and involves 13,000 drill holes (215,000m of drilling) and injection of 85,000 tonnes of grout in a tight 6 month contract period. Up to 22 drilling rigs are on site.


November 2008
 

Network Rail Principal Contractors Licence & Link –up Accreditation

Our Contractors Assurance Case has now been replaced with a Principal Contractors Licence. In addition we have extended our accreditation under Link-up product to include 103 separate product groups. (See ‘Company Profile’ for full listing).


October 2008
 

ISO 9001, ISO 14001, OHSAS 18001 Accreditations

We have successfully completed our 3 year re-audits for the three management systems standards which are accredited through AJA Registrars. As the next step in our continuous improvement objectives we are preparing for assessment under the Investors in People standard which will recognise our commitment to training and development of our staff & employees.


August 2008
 

Drilling Rig Guarding.

Following advice to the drilling industry from the Health & Safety Executive we have now completed installation of interlocked guards to prevent accidental entanglement with drilling equipment on all our rotary and rotary percussive drilling rigs and also to our rotary and auger mini-piling rigs.


July 2008
 

Severn Trent Water.

Our AMP 4 Sewerage framework for Severn Trent Water continues apace with the focus on delivering UID’s and Flood Relief Schemes and we have a sizeable portfolio of projects to complete by March 2009 in the West Midlands, Warwickshire, Worcestershire and Gloucestershire.


April 2008
 

International Safety Award 2007.

The Company has received the British Safety Council ‘International Safety Award’ for 2007. This is the 7th successive year that we have scooped this prestigious safety award from one of the worlds leading training and advisory bodies and is continuing recognition of our pursuit of excellence in health & safety at work.


March 2008
 

Achilles Verify Audit.

Our Achilles UVDB ‘Verify’ audit was carried out during March and excellent scores ranging from 93% to 100% were achieved for our Quality, Environmental and Health & Safety practices and procedures.


February 2008
 

Record Turnover Achieved.

2007 has proved to be another successful year for the company with turnover exceeding £32m for the first time. The sustained level of turnover is largely due to increased levels of work in our key market sectors of ground engineering, remediation, water utilities and development infrastructure.


September 2007
 

Mini-Piling.

Mini-Piling & Drilling are about to commence their largest contract awarded to date – a £238k scheme in Scotia Rd, Stoke-on –Trent for installation of 101no x 324mm diameter driven steel cased piles together with ground slab as part of a new industrial development for O-Gen UK Ltd.


September 2007
 

Pemberton Stadium Development, Llanelli.

The 2 phase £2.6m mine workings treatment scheme for the Pemberton Stadium Development, Llanelli for Walters UK is nearing completion. Commenced in 2006 we are about to commence stabilization work on the smaller second phase of the scheme. Work has included over 4000 drill holes, 9000tonnes of grout and treatment of 15 mineshafts. 10 drilling rigs were resourced to site for the main work.


August 2007
 

New Appointments.

We are pleased to announce the following appointments to key business support areas within the group;

  • Jane Sweeney – Marketing Manager
  • Martin Chivers – SHEQ Manager

  • August 2007
     

    Top Rain/511 Sites, Hawthorne Rd, Bootle.

    These heavily contaminated ex-industrial sites are being reclaimed and developed for housing by Bellway Homes in partnership with Sefton Council as part of their Pathfinder Housing Market Renewal Initiative. We have already completed extensive remediation work on the sites and are currently constructing the infrastructure, piling and foundations for the development. Contract value £8.0m.


    July 2007
     

    Geothermal Boreholes at Oxford Hospital.

    We have recently completed installing a field of 73 geothermal boreholes each 100m deep at the new Churchill Hospital, Oxford, a PFI funded scheme in which Haden Young are the main M&E contractor. The holes were drilled by our Casagrande C6S ’dual head’ rigs which allow fully cased holes to be drilled through any ground conditions ensuring a clean hole for loop installation & grouting.


    July 2007
     

    Chatterley Valley, Stoke-on Trent.

    We recently commenced remediation work on the Lowlands Road site at Chatterley Valley for Advantage West Midlands. The 14 ha site is part of AWM’s extensive commercial and industrial redevelopment plans for the Chatterley Valley area. The £1.25m scheme involves extensive earthworks, soil stabilization, mineshaft treatment, brookcourse realignment, water features and environmental mitigation works.


    May 2007
     

    Award of major Groundworks and Infrastructure contract for Aldi at their Regional Distribution Centre in Swindon.

    A £6.3m Groundworks & Infrastructure contract for extensions to the warehouse, chiller & freezer units and provision of new offices at Aldi’s existing distribution centre involves; earthworks, foundations, reinforced concrete ground slabs, walls and suspended slabs, pre-cast concrete panel installation, foul and surface water drainage including on-site surface water retention tanks, external works for loading bays, access roads and car park areas. The 52 week contract commenced in April.


    April 2007
     

    International Safety Award 2006

    The company has been given the British Safety Council ‘International Safety Award’ for 2006. This is the 6th successive year that we have scooped this prestigious safety award from one of the worlds leading training and advisory bodies and is recognition of our pursuit of excellence in the management of Health & Safety.


    March 2007
     

    Record Turnover Achieved

    2006 has proved to be the most successful year to date for the company with turnover exceeding £30m for the first time. The growth in turnover is largely due to increased levels of work in the ground engineering and remediation sectors.


    February 2007
     

    Chettles Development, Radford, Nottingham

    A £1.75m contract to remediate a 3.6ha heavily contaminated industrial site and provide new infrastructure for a proposed student accommodation village has been awarded by Ocon Construction Ltd (part of The Opal Property Group). The 40 week contract commenced on 26th February.


    February 2007
     

    Myreside Street Development, Glasgow – Mineworkings Treatment

    We recently commenced this £1.4m mineworkings stabilisation contract for Bellway Homes (Scotland). The scheme involves drilling 6000 grout holes (160,000m of drilling) and injection of up to 35,000 tonnes of grout and will be completed in 18 weeks.


    September 2006
     

    Rail Contractors Assurance Case Award

    The company was awarded its Rail Contractors Assurance Case (CAC) by Network Rail on 22nd September 2006 allowing us to carry out work on Network Rail controlled infrastructure. The CAC covers a range of work types also covered by its Link-up accreditation including; Major Civil Engineering, Minor Civil Engineering, Earthworks – Embankments & Cuttings, Ground Anchors, Piling, Geotechnical Engineering Contractors, Lineside Structures – Brick & Concrete, Thrustboring & Pipejacking, Specialist Drilling Engineers and Other Civil Engineering.


    September 2006
     

    Mini-Piling & Drilling Ltd Launch

    As from the 1st of September 2006 the Mini-Piling services provided by the company will be operated under the name Mini-Piling & Drilling Ltd. Enquiries for our extensive range of mini-piling services which include Driven Steel Cased, Odex, Augered and CFA Piles should be made to Mark Tromans – Piling Manager


    August 2006
     

    Quedgley Urban Village Requisition Sewer

    We have recently been awarded the £1.3m Quedgley Urban Village Requisition Sewer, Gloucester, by Severn Trent Water. The 500m of 1200mm diameter sewer is being installed by machine driven pipejack and will service a large new residential development on the north east side of Gloucester.

    In addition we have secured the £2.8m contract to treat mineworkings and mineshafts on the Pemberton Development, a major retail and commercial development in Llanelli, South Wales. The contract is being carried out for Walters UK Ltd and involves a fleet of 12 drilling rigs to drill the anticipated 6400 grout holes.


    August 2006
     

    Mart Lane Bridge Opening

    The 22nd August 2006 saw the opening of Mart Lane Bridge in Stourport on Severn, Worcetershire, by the Mayor of Stourport. The new heritage style ‘hump back’ bridge together with the reconstructed canal arm and mooring basin has been constructed as part of a reclamation and residential development involving Woodford Group and British Waterways


    April 2006
     

    International Safety Award 2005

    The company has been awarded the British Safety Council International Safety Award for 2005. This is the 5th successive year that we have secured this prestigious award and is recognition of our commitment to Health & Safety.

    March 2006
     

    Mini-Piling Services

    We have significantly extended our mini-piling services and capabilities following the addition of 16 compact mini-rigs offering a range of drop hammer, odex and augered piles. Our piling services are managed by Mark Tromans who has over 25 years experience in this field. (See ‘Mini-Piling Services’)

    January 2006
     

    Contractors Assurance Case – Network Rail

    The scope of work carried out by the company is ideally suited to the range of civil and ground engineering work carried out on Network Rail Infrastructure. We are currently developing our Contractors Assurance Case under sponsorship from Network rail which we expect to have in place by October 2006.
     

    January 2006
     

    Business Development Executive appointed

    Bernard Hardisty, former Head of Land and Property with Advantage West Midlands and Senior Development Executive with English Partnerships has been appointed to develop key business growth areas including derelict and contaminated land remediation and development.

    December 2005
     

    Award of major Groundworks and Infrastructure contract for Aldi Head Office and Distribution Centre Expansion

    In December 2005 we were awarded the £4.5m Groundworks & Infrastructure contract for extensions to the existing distribution centre and head office facilities at Atherstone, Warwickshire. The 32 week contract includes earthworks, soil improvement, CFA piling, foundations, drainage and reinforced concrete slabs & retaining walls. We have recently completed a similar project for a new Aldi distribution centre in Neston, Wirral. (See ‘Project Profiles’)

    November 2005
     

    Awarded Accreditation to OHSAS 18001:1999

    Our accreditation to the Occupational Health & Safety Management Standard in November 2005 is part of our ongoing business improvement plan. Our integrated Quality, Environmental and Health & Safety management systems are operated on all sites.

    August 2005
     

    Awarded £7m Mineworkings Treatment Project for M9 Spur  Extension for Edinburgh City Council

    In May 2005 we were awarded the advance works contract to drill & grout several extensively mined oil shale workings beneath the route of the proposed M9 Spur Extension/A90 Upgrading, linking the Forth Road Bridge. The 52 week contract commenced in June 2005 and is using specialist ‘simultaneous casing’ drilling methods to ensure full treatment of the workings. (See ‘Project Profiles’)

    April 2005
     

    Severn Trent AMP4 Sewerage Framework Contract (2005 – 2010)

    Following the successful completion of our AMP3 Sewerage Framework Contract (2000 – 2005), we are now one of Severn Trent Waters framework sewerage contractors for their AMP4 capital expenditure programme. (See ‘Project Profiles’)

       

    Valid XHTML 1.0 Transitional
    Valid CSS!

    Forkers Limited
    Registered in England No 1073245
    Mini-Piling & Drilling
    Company Ltd
    Registered in England No 5706455

    Registered Address: Golds Green House, Shaw Street, West Bromwich, West Midlands B70 0TX
    Tel: 0121 505 1010 Fax: 0121 505 1026
    e-mail: admin@forkers.com Web: www.forkers.com